Minister of Railways Shri Suresh Prabhakar Prabhu inaugurated Passenger amenities at Adarsh Station – Salauna and commenced the following works through video conferencing from Rail Bhavan today –

  1. Doubling of Hajipur – Bachwara
  2. Doubling of Samastipur- Darbhanga
  3. 3rd Line of Patratu (Dhanbad) – Sonnagar

Chairman, Railway Board, Shri A. K. Mital and other Railway Board Members and senior officials of Railway Board were present on the occasion.

 DOUBLING OF HAJIPUR-BACHHWARA (72 Km)

1.GENERAL:

            Year of Sanction         : 2015-16

            Sanctioned Cost          : Rs. 678.54 Crore

2.BENEFITS:

HAJIPUR-BACHHWARA section is located on Hazipur- Barauni high density route on East Central Railwayand is an alternative shortest route for traffic movement towards N.F. Region. The  traffic utilization of the section is 120.45% with maintenance blocks. The doubling between Hajipur and Bachhwara will remove capacity constraint and help to attain the fluidity of traffic movement.

3.Present Status of the Work:

The project is being executed by IRCON. Tender for Earthwork, Minor & Major bridges has been awarded.

DOUBLING OF SAMASTIPUR – DARBHANGA (38 Km)

1.GENERAL:

            Year of Sanction         : 2015-16

            Sanctioned Cost          : Rs. 491.01 Crore

2.BENEFITS:

SAMASTIPUR – DARBHANGA section is located in between Samastipur – Narkatiaganj route and is an alternative shortest route for traffic movement towards N.F. Region from Gorakhpur. The traffic utilization of the section is 235% with maintenance blocks and heavy detention to freight traffic. The doubling between SAMASTIPUR – DARBHANGA will remove capacity constraint and help to attain the fluidity of traffic movement.

3.Present Status of the Work:

The project is being executed by EC Railway. Agency for Earthwork, Minor & Major bridges up to 15 Km has been fixed.

PATRATU – SON NAGAR 3RD LINE PROJECT (291 Km)

1.GENERAL:

            Year of Sanction         : 2016-17

            Sanctioned Cost          : Rs. 3406.16 Crore

 2.BENEFITS:

The project will cover Ramgarh, Hazaribagh, Latehar, Palamu & Garhwa districts of Jharkhand and Aurangabad district of Bihar and will provide for effective transportation of Food grain, Iron ore, Coal, Fertilizer, Cement and Sugar.

3.Present Status of the Work:

The project – 3rd Line between Sonnagar-Patratu has been sanctioned in Dec.’2016 at the cost of Rs 3406.16 Crore. The project has been entrusted to   RVNL for execution. Two Project Implementation Units (PIUs) of RVNL at Ranchi and Mughalsarai are being set up. Detailed Planning for inviting Tenders is being done.

Source : PIB

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Discover more from Govtempdiary

Subscribe now to keep reading and get access to the full archive.

Continue reading